Once you know a solid roof on your conservatory needs building regulations approval, the next question lands quickly: which kind of application? A firm may ask you, or tell you which one they use, and the two names do not explain themselves.
Here is what each one means, and why the choice is less about paperwork than about who carries the risk.
Why a solid roof needs approval at all
A glazed conservatory is exempt from the building regulations as long as it stays a conservatory. Put an insulated, tiled roof on it and that changes. In LABC’s words, more or less: tile it and insulate it, and the old exemption no longer protects the job.
From then on the work answers to the regulations, and inspectors will ask whether the old uprights, door spans and footings can hold so much more weight. There are two ways for that scrutiny to happen.
Full plans
With a full plans application, detailed drawings go to building control before any work starts. Those drawings are assessed, and a decision is owed within five weeks; with your consent the council can stretch that to two months.
Once approved, you get an approval notice, the work is inspected as it goes, and a completion certificate follows at the end. The point of it is that problems show up on paper, where they are cheap to fix, rather than on site.
Building notice
A building notice skips the up-front drawings. Two days after lodging it, builders may begin, and the inspector judges compliance on visits to the site.
It suits smaller, simpler domestic jobs, and plenty of conservatory roofs are done this way. The catch is that nothing is approved in advance. If an inspector finds something that does not comply, the work may have to be altered, and the owner carries that risk.
The two side by side
Here is a quick comparison, drawn from the Planning Portal and council guidance listed at the end.
| Full plans | Building notice | |
|---|---|---|
| Drawings needed first | Yes | No |
| When work can start | After approval, or at your own risk sooner | 48 hours after submitting |
| Decision time | Five weeks (two months if agreed) | Nothing to decide up front |
| Who carries the risk | Lower, as plans are approved first | Higher, as problems surface on site |
| What you get at the end | Completion certificate | Completion certificate |
Some work must go through full plans regardless, for example building over or near a public sewer. A firm that has looked at your garden should flag that.
Which suits a conservatory roof?
For a straightforward roof on a conservatory with a solid base and a sturdy frame, a building notice is common and works well. Where there is doubt about whether the frame or the foundations can take the weight, many people feel happier with full plans, because the structural questions get answered before the old roof comes off.
A quick way to decide: ask yourself what happens if the inspector is not happy halfway through. If the answer is a cold, open conservatory for weeks while it is sorted out, the extra time for full plans can be worth it.
Who applies, and what it costs in Sheffield
In a lot of cases the roofing firm makes the application, either with the council or with a registered building control approver, and builds the fee into its price. Others leave it to you. Either way, the approval is tied to your home, so make sure the completion certificate ends up with you.
Sheffield City Council Building Control publishes its charges on the council’s fees and charges page. Our fee study looks at what is published, and the building regs page covers planning too.
If work was done without approval
Inherited a solid roof that nobody ever had signed off? Regularisation is the fix. It applies to work already done and is judged after the event. It is worth knowing about if you are buying a house in Sheffield with a solid-roofed conservatory and no paperwork.